An ordered queue: reform of the GB grid connections process
24 February 2025

24 February 2025
The new National Energy System Operator (NESO) is taking forward significant reforms of the electricity grid connections process, which are scheduled to go live in the second quarter of 2025. The connections reforms – often referred to as the TMO4+ reforms – are intended to address the connection delays currently resulting from the existing "first come, first served" connection applications model, and achieve the goals set out in the Government's Clean Power 2030 Action Plan (CP30 Action Plan). The reforms will have implications not just for new connection applicants, but also for most projects that currently hold a connections offer to connect to the transmission or distribution system.
The regulator, Ofgem, published a consultation on 14 February 2025, setting out its "minded to" decision to approve the key elements of the TMO4+ reforms – those elements being the code modifications CMP434 and CMP435 (relating to the Connection and Use of System Code (CUSC)), CM095 (relating to the System Operator Transmission Owner Code), and the three Connections Methodologies: Gate 2 Methodology, Connections Network Design Methodology, and Project Designation Methodology. This latest development brings the reforms one step closer to implementation. In parallel, there are also other code modifications that have been raised and which are relevant in this context – in particular, CMP448, which seeks to implement a new financial instrument requirement for connection applicants.
In this briefing we set out a summary of the key elements of the reforms, implications for different categories of projects and the timetable for implementation of the reforms.
NESO's predecessor, National Grid Electricity System Operator (NGESO) first paved the way for the reforms currently being implemented with its "five-point" plan, which was launched in early 2023.
The five-point plan represented interim solutions to the queue, and was made up of the following elements:
The ENA, which represents Distribution Network Operators (DNOs), also implemented reforms to address connection delays for developers seeking connection to the electricity distribution network. This plan comprised:
In November 2023, Ofgem and the Department for Energy and Net Zero published a joint "Connections Action Plan", which set out a vision for a connections process that "should facilitate viable projects to connect in line with their required timeframes and the required pathways to net zero". Significantly, the Plan outlined how grid connections reform would be implemented, with a dedicated Connections Delivery Board (comprising representations from Government, Ofgem, NGESO, network companies, the ENA and industry), and Government and Ofgem working closely with NGESO (now NESO) and the DNOs.
The new regime being implemented through the connections reforms means that most projects seeking a new connection (or a modification to an existing connection) to the transmission or distribution system will no longer be able to apply at any time to secure a place in the connections queue. Instead, there will be set application windows. To secure a place in the queue, applicants will need to meet certain Gate 2 criteria. Applicants that are unable to satisfy the Gate 2 criteria may be eligible for a Gate 1 connection offer, which serves to provide only indicative connection details.
The Gate 2 criteria, set out in the Gate 2 Criteria Methodology, are made up of two elements:
The only projects not impacted will be demand projects seeking a connection to the distribution system or very small generation projects seeking a connection to the distribution system (as these have no significant impact on the transmission system). The small embedded generation projects which will not be required to apply for a Gate 2 offer are projects under the lower limit Transmission Impact Assessment (TIA) thresholds – the current lower limit TIA is 1MW in England and Wales and 200kW in Scotland South and Scotland North.
Before the enduring arrangements commence, NESO will carry out a one-off exercise – the "Gate 2 to Whole Queue" (G2WQ) process – to determine which projects that currently hold a connection offer satisfy the Gate 2 criteria. Recognizing that the G2WQ process will apply retrospectively to many connection offer holders, projects that currently have a connection offer and that fall within certain exceptions (set out in more detail below) will be considered to satisfy the Strategic Alignment Criteria.
In terms of the general architecture of the new regime, there are three new documents (referred to as methodologies) that the NESO has consulted on and which the NESO will be required to maintain pursuant to its licence. These are:
In parallel, amendments are also being made to the CUSC to implement the regime, as well as various other code and licence condition amendments.
In preparation for implementation of the new regime, since 2 September 2024, any new applications for a direct connection to the transmission system have been receiving a so-called "Transitional Offer". These Transitional Offers have been similar in nature to the "Gate 1" offers being introduced as part of the connections reforms (see below). In particular, Transitional Offers have only included an indicative connection date and an indicative connection location. As the application will not have been studied, no reinforcement works will be included or associated securities required.
The Transitional Offers process was not applied to BEGA, BELLA1 or modification applications.
On 15 January 2025 NESO announced a "pause" on accepting new applications from 29 January 2025 (subject to some exceptions). The pause is intended to allow NESO to get ready for implementation of the Connections Reform and therefore applies until the point at which Connection Reform is implemented or Ofgem states that it is not proceeding with the reforms (whichever happens first). The pause will apply to new applications, modification applications, BEGA and BELLA applications and Project Progressions2. While Distribution Network Operators (DNOs) and Independent DNOs (IDNOs) will continue to accept and process applications for connection to the distribution system, they will not pass them through to NESO for transmission impact assessments.
Connection applications that will not be impacted by the pause are as follows:
For applications submitted by 29 January, NESO and the TOs will endeavour to clock start those applications before 12 February. Significantly, any applications that have not clock started by 12 February will not be processed (unless they fall into one of the exceptions listed above).
For projects that miss the 29 January deadline, the next opportunity to apply for a connection will be when the first application window under the new regime opens – NESO has said this is likely to be in Q4 2025.
The applicant, through a Readiness Declaration, will be required to provide evidence that the project is "ready" by demonstrating compliance with the Readiness Criteria, which can be demonstrated through one of the following two routes: the project acquiring appropriate land rights or going through the Development Consent Order process – as summarised in Figure 1. The full details are set out in the Gate 2 Criteria Methodology.
Route for satisfying Readiness Criteria | Details |
Land | Applicant must:
|
Planning | Applicant must have a submitted and validated application for planning consent in accordance with the Development Consent Order process, which allows the applicant to be granted Compulsory Purchase Order powers. |
The Government's Clean Power 2030 Action Plan (CP30 Action Plan) plays a key role in establishing the Strategic Alignment Criteria.
The CP30 Action Plan sets out the capacity range for the main technologies that are expected to be deployed to allow the clean power objectives to be met, and which will therefore inform the prioritisation of projects for grid connection. As well as setting out the capacity ranges for the period up to 2030, the plan also sets out indicative capacity ranges for the period up to 2035. It is intended that a Strategic Spatial Energy Plan, to be published next year, will set out a longer-term spatial plan, building on the 2030 capacity ranges set out in the CP30 Action Plan. See Figure 2 below for the 2030 capacity ranges.
Technology | Offshore wind | Onshore wind | Solar | Nuclear | Low Carbon Dispatchable Power | Unabated gas | LDES | Batteries | Interconnectors |
Current installed capacity (GW) | 14.8 | 14.2 | 16.6 | 5.9 | 4.3 | 35.6 | 2.9 | 4.5 | 9.8 |
Clean Power Capacity Range (GW) | 43-50 | 27-29 | 45-47 | 3-4 | 2-7 | 35 | 4-6 | 23-27 | 12-14 |
The CP30 Action Plan, published in December 2024, will in the future be replaced by longer-term plans for the GB energy system, as summarised in Figure 3.
Strategic Spatial Energy Plan (SSEP) | This will be developed by the NESO to spatially map out the energy assets necessary to meet 2050 objectives, building on the CP 2030 Plan. This is due in 2026. |
Centralised Strategic Network Plan (CSNP) | In parallel with the SSEP, the NESO will develop a gas and electricity transmission network plan out to 2050. The CSNP is due in 2027. |
Regional Energy Strategic Plans (RESPs) | The SSEP will also interact with and inform RESPs – and vice versa. |
For most projects (in particular, the technologies covered by the CP30 Action Plan), the primary way of satisfying the Strategic Alignment Criteria will be through alignment with the generation technology capacities set out in the CP30 Action Plan – in effect, by fitting within the relevant "technology pots", as described in more detail in Figure 4. However, there are also other ways that projects can satisfy the Strategic Alignment Criteria, including protections for projects currently being progressed. The different alternative routes to satisfying the Strategic Alignment Criteria are summarised in Figure 4, with full details set out in the Gate 2 Criteria Methodology.
Route to satisfying the Strategic Alignment Criteria | Key document | Details |
Certain "protections" for existing connection offer holders | Gate 2 Criteria Methodology | Projects relying on this route will need to fall within one of the following categories (described as "clauses"):
|
CP30 Action Plan | Connections reform annex of CP 2030 Plan | Applies to offshore and onshore wind, solar, nuclear, low carbon dispatchable power, unabated gas, Long Duration Energy Storage (LDES), batteries, interconnectors. Projects will need to fall within the capacity ranges set out in the plan for individual technologies, for Phase 1 (2026-2030) and Phase 2 (2031-35). These capacity ranges are GB-wide, except for solar, onshore wind and batteries – for these technologies, the capacity ranges are set for 11 transmission zones and 8 distribution zones (noting that for onshore wind, the zonal split only applies for Phase 1). Where there is under-supply against capacity ranges up to 2030, NESO will look first to substitute viable projects of the same technology from adjacent, over-supplied, zones. |
Designation in accordance with the Project Designation Methodology | Project Designation Methodology | Certain projects can satisfy the Strategic Alignment Criteria by making an application to be designed by the NESO if they fall within one or more of the following categories:
For categories A to C, NESO will publish a notice when it considers that projects within those categories are needed. |
Projects not within the scope of the CP30 Action Plan, but which are listed in section 6.3 of the Gate 2 Criteria Methodology | Gate 2 Criteria Methodology | The following categories of projects are outside of the scope of the CP30 Action Plan and are considered to automatically meet the Strategic Alignment Criteria:
|
Current expectations are that the G2WQ process will commence in Q2 2025, and Gate 2 offers will then be issued to projects by the end of 2025. NESO will publish the timetable for the application window and other details, such as other key dates and milestones. The Connections Network Design Methodology sets out details of how the G2WQ process will be carried out. At a high level, the process will involve the following:
Following the one-off G2WQ process, NESO will hold Gate 2 application windows twice a year. Full details on timing have not yet been provided.
Projects that are unable to satisfy the Gate 2 criteria at the time of application will also have the option of applying for a Gate 1 offer instead. A Gate 1 offer will include only an indicative connection date and an indicative connection location (unless the project is selected for connection point and capacity reservation). Importantly, an application for a Gate 1 offer is not a prerequisite to a subsequent application for a Gate 2 offer. Moreover, only transmission connected projects and large embedded projects are eligible to apply for a Gate 1 offer (see below).
It is proposed that for small and medium embedded generators, DNOs will carry out initial checks on whether projects satisfy the Gate 2 criteria and will then follow a process largely based around the Project Progression process that currently applies. The Statement of Works process is being removed, with Transmission Evaluation being introduced as a route for a DNO to request an Evaluation of Transmission Impact. DNOs will submit a Transmission Evaluation Application to NESO on behalf of their embedded customers, within the Gate 2 application window. The application can contain multiple embedded generator projects or one submission per embedded generator project.
Large embedded generators will be able to apply for a BEGA/BELLA Gate 2 offer throughout the year, but the DNO will still need to submit a modification application (for transmission assessment) in the Gate 2 application window. NESO will verify whether a project has met the Gate 2 criteria as part of the processing of the BEGA/BELLA application. If a large embedded generator wishes to receive a Gate 1 offer prior to having met the Gate 2 criteria, it must submit the BEGA/BELLA application to NESO in the Gate 2 application window, but no modification application is needed from the DNO – the large embedded generator will receive a Gate 1 offer from NESO based on their BEGA/BELLA application.
The ENA has advised that DNOs are still evaluating what approach will be taken in relation to projects that are not successful in securing a Gate 2 offer but are not eligible for a Gate 1 offer.
As part of other adjustments related to the main connections reforms, NESO in January 2025 NESO raised a further CUSC modification proposal (CMP446) to increase the lower threshold for the Evaluation of Transmission Impact Assessment. It has been proposed by NESO that this lower threshold applying in England and Wales should be increased from 1MW to 5MW. It is intended that this modification should be implemented before the G2TWQ process is commenced. If it is, then, according to NESO, this would relieve around 400 distributed generation projects from having to demonstrate Gate 2 compliance. To expedite the process, Ofgem has consented to this modification proposal being treated as urgent.
As part of the proposed connection reforms, NESO has also been considering the introduction of a new requirement for Gate 2 offer holders to provide financial security (referred to as a "financial instrument"), to further signal their commitment to progressing their project. NESO published a "call for input" on these proposals in November 2024.
Following this call for input, NESO has now raised a new CUSC modification (CMP448) to introduce a Progression Commitment Fee (PCF) that will support future connections in the queue. The PCF will only apply to generation projects that have already progressed through the first stages of the connections process to join the future Gate 2 connections queue but have not yet initiated statutory consents and submitted a planning permission which is a requirement of Milestone 1 (which is one of the "User Progression Milestones" referred to above).
Under the proposals, NESO has indicated that the PCF will remain dormant unless a metric, which is indicative of the health of the connections queue exceeds a defined threshold. The proposed PCF applicable to a project will have an initial value of £2,500/MW, increasing at a rate of £2,500/MW at 6 monthly intervals up to a maximum of £10,000/MW for any individual project. Projects will be liable for the full value of their PCF upon termination of the project (or the appropriate portion of the PCF upon reduction of capacity) prior to successfully demonstrating achievement of Milestone 1.
If the PCF is activated, developers of projects between Gate 2 and Milestone 1 will be required to post a security against the PCF, the “Progression Commitment Fee Security” (PCFS). The PCFS must remain in place until the developer successfully demonstrates that the project has achieved Milestone 1. After achieving Milestone 1, developers will no longer be subject to the PCF if they terminate and there will no longer be a requirement to secure against the PCF.
It is currently contemplated that if Ofgem agrees, this modification will be treated as an "urgent" modification, so that it can follow an expediated timetable.
Ofgem's consultation on its "minded to" decision to approve the TMO4+ proposals closes on 14 March 2025. Ofgem expects to make a final decision by the end of Q1 2025 (or as soon as possible after that). Ofgem is also carrying out a separate consultation on modifications to the electricity transmission, distribution and Electricity System Operator licence conditions, that Ofgem considers are required to implement the reforms. This consultation is also closing on 14 March 2025.
Authors: Justyna Bremen, Counsel; Antony Skinner, Partner; Hannah Roberts, Associate
The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
Readers should take legal advice before applying it to specific issues or transactions.